The majority of the site work will take place around the clinic this week. Continuing on from last week, the crews will be prepping for the vestibule footing prep and the interior framing. New this week, the fire suppression system will begin to be installed.
The lecture hall framing will also continue and the slab on grade mechanical, electrical, and plumbing rough in at LINAC.
While the to-do list is short this week, these are major components of the Magruder Expansion and we’ll start noticing more physical changes in the project.