As Thanksgiving is upon us this coming Thursday, November 22nd and we gather with our friends and family, the University will be observing the holiday on both the 22nd and 23rd.
Fortis and their fantastic subcontractors will also be taking Thursday-Sunday off to spend time with their loved ones. Construction will be up and running at full force Monday the 26th.
During this 3-day week, there will still be plenty happening on site. At the clinic location, the CMU installation will continue as they plan to wrap up at the end of next week.
Over at the location for the new lecture hall, Pacific Excavation will continue laying the underground storm and sewer piping and will tie in to the main sewer line on Wednesday the 21st.
T. Gerding will continue to form the walls at the LINAC addition for the next several weeks and the structural rebar will be delivered Wednesday. So please be aware of moving equipment in the hospital parking lot.
Overall, Hammerquist will still be working on their investigation and routing for plumbing and E.C. Electric will be working on the electrical piping inside the building.
Happy Thanksgiving, from our team to yours!
For an updated schedule and pictures, please see the tabs above!