For the new clinic, this week Fortis will be working on the slab edge forming and the slab rebar installation in preparation of an early morning concrete slab on grade pour starting at 4 am Friday the 19th.
In the parking lot, they will be clearing out the island to make room for additional clinic parking.
On the other side of Magruder, the lecture hall will have the electrical and plumbing roughed in. Also, they will be excavating for the footing for the LINAC addition.
to check out updated photos and the 4 week outlook schedule click the photos tab at the top of the page.