Monthly Archive for February, 2010

Monday February 15, 2010

Hello all, Well I guess I should of “knocked on wood” when on Friday I wrote “All is well in the Memorial Union”. Another steam leak has been found. This one is located under the ice machine in the Ballroom servery. This is the 3rd steam leak within 40′ of the same pipe. We will wait [...]

Read Full Post »

  Okay, typing that header felt really good! Since starting the daily information letters I have never been able to use that headline. Of course we are still taking care of the daily repairs and work requests; there will always be those. But, the emergent issues are taken care of. The pipe under the Ballroom floor is [...]

Read Full Post »

Wenesday February 10, 2010

MU East / Craft Center; The kiln project was finished today. The new ventilation system is taking the hot air from the kiln 25 feet away from the building. This means no more pollutants in the Craft Center. Air handler; The parts came in for the air handler in the main lounge. The students installed [...]

Read Full Post »

Changes in closures

Hello All, The perimeter heat will be turned off and on for probably most of the day. We have found some more steam leaks and will be working on them. If you feel it getting cold, never fear, it will warm back up. Also, Hammerquist will not be here today to work on the pipe [...]

Read Full Post »

Monday Febuary 8th, 2010

!!!Tomorrow is still scheduled for the West end bathroom closeure!!! WATER LEAK As I notified last week, the pipe under the Ballroom floor is going to be under repair tomorrow. Scott from Hammerquist will be here to help Jay and Company pull the pipe and check it for leaks, cracks and pits. This is going [...]

Read Full Post »

Yesterdays News

Thursday Building Update Good afternoon all, Today’s update is brought to you by way of Cindy and Sid (the man has a way with words). Why recreate the wheel…right? However, I do have something to add. Yesterday afternoon Kent asked me if I would like to turn the Building Update letters into a blog. This [...]

Read Full Post »

Hello All,   To follow in Sid’s footsteps, I’ll start by saying the problems continue to shrink and as of this afternoon things are definitely looking up! However, there is still work and repair going on in and around the building. To keep things simple, I will list the areas that may affect you tomorrow. [...]

Read Full Post »

Wednesday Dec 30, 2009

Wednesday update:   Dock drain closed until further notice.  A hose has been set up to use on the west end of the compactor where the apron drain is located.  Dye testing showed up in the servery sump and further looking found that line collapsed.  An alternate drain idea has yet to come forward… We [...]

Read Full Post »

Tuesday Dec 29, 2009

Tuesday update:  0900: Elevator 2 down, door assembly.  George, new elevator tech on campus, is on scene.  Nice fellow, from Thyssen.  Been here since 30 November. Allan Bros. in to Java Stop for scheduled maintenance. Andrew Gray came in to inspect the asbestos in the Women’s RR work, standing by for further details to scope [...]

Read Full Post »

Monday Dec 28th, 2009

Monday update: Shawn from Roto-Rooter scheduled in at 0900 Tuesday to tv the line or the tunnel, whichever works.  Bob Z. and Bret will be on hand to assist. Contacted Scott from Hammerquist to perform necessary repairs.  Scott will need the runnel clean before repairs can commence. Contacted Joe Rivera, President, Advanced Recovery Systems Inc. [...]

Read Full Post »