Primary construction activities for the week of 12/09 thru 12/13 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue framing soffit
  • CANOPIESWest Canopy V102:Finish installing electrical and gyping lids *Installing WRB
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Continue installing trim and wood soffit
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Continue finishing siding *
  • INTERIOR BUILDOUT
  • Commons Wing – Auditorium:
    • Start installing electrical
  • Commons Wing – Innovation Lab:
    • Painting
    • Installing ACT grid
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish installing MEP in hard lids
    • MEP inspection
    • Start gyping walls and lids
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Installing ceiling grid and MEP in ceilings
    • Inspection for MEP in ceilings
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finishing lids and walls
    • Painting and installing ceiling grid in Sound Control
  • Lab Wing – Level 1 – Mechanical & Back of House:
  • Continue installing panels and feeders in electric rooms
  • Lab Wing – Level 1 – Commons Spaces (Café & Fireplace):
    • Installing transformer and panels
    • Start grinding floors and install electrical in walls
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish installing MEP at hard lids *
    • MEP inspection for hard lids *
    • Start gyping walls and lids
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Installing casework and windowsills
  • Lab Wing – Level 2 – Labs:
    • Finish overhead electrical in lab area
    • Completing floor moisture mitigation
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid
  • Lab Wing –  Level 3 Rough-in:
    • Gyping South and East walls
    • Finishing walls, OTS insulation, and top-of-wall at SE area
    • Start gyping North walls
    • Installing electrical on North and West
    • Start installing MEP in OTS, offices, and SE area
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Start installing disconnects

Primary construction activities for the week of 11/25 thru 11/29 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue framing soffit *
    • Continue installing metal siding
  • CANOPIES West Canopy V102:Finish installing electrical and gyping lids *WRB start delayed
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Start installing trim and metal soffit panels *
  • WINDOWS & SIDING
  • Auditorium – East Elevation:
    • Installing beauty cap and flashing
  • Auditorium – North Elevation:
    • Continue finishing siding in Armpit
  • Auditorium – South Elevation:
    • Continue finishing siding
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish MEP in walls
  • Finish installing balance of drywall
  • Continue installing MEP in 1st floor corridors *
  • Start installing 1.5” metal deck *
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Continue finishing lids and walls *
  • Lab Wing – Level 1 – Rough-in:
  • Continue installing overhead MEP work in OTS
  • Lab Wing – Level 1 – Commons Spaces:
    • Finish installing MEP in fireplace cavity *
    • Starting gyping walls *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish installing MEP at hard lids *
    • MEP inspection for hard lids
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Continue finishing MEP in grid
  • Lab Wing –  Level 2 – Commons Spaces:
    • Finish polishing floors
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Grinding floors
  • Lab Wing –  Level 3 Rough-in:
    • Finish installing gyp top-out at Donut
    • Start completing balance of MEP in walls
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Disconnects install delayed
  • Elevator 2:
    • Continue installing elevator

Primary construction activities for the week of 11/18 thru 11/22 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • Low Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Finish framing soffit
    • Continue installing metal siding
  • CANOPIESEast Canopy V103:Finish installing frames and glass **
  • South Canopy V101:Finish installing frames and glass **
  • West Canopy V102:Finish installing electrical and gyping lidsFinish installing WRB *
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Start installing trim and metal soffit panels *
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Continue finishing siding after soffit is complete
  • Auditorium – West Elevation:
    • Installing beauty cap and flashing
  • Auditorium – North Elevation:
    • Finish installing glass and pressure bar
    • Start installing beauty cap and flashing *
  • Auditorium – East Elevation:
    • Finish finishing siding *
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish installing MEP in 1st floor corridors *
  • Start installing 1.5” metal deck *
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Start installing MEP in ceiling, inspecting MEP in ceilings, and installing ceiling tiles *
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish finishing lids and walls *
  • Lab Wing – Level 1 – Rough-in:
  • Finish painting top out and OTS **
  • Start installing overhead MEP work in OTS *
  • Lab Wing – Level 1 – Commons Spaces:
    • Finish installing fireplace and MEP in fireplace cavity **
    • Starting gyping walls *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish framing hard lids **
    • Start installing MEP at hard lids *
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Start finishing MEP in grid *
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Finish finishing gyp *
    • Painting
  • Lab Wing –  Level 3 Rough-in:
    • Finish installing MEP in walls at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Start installing disconnects *
  • Elevator 2:
    • Continue installing elevator

Primary construction activities for the week of 11/11 thru 11/15 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • Low Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Continue framing soffit *
    • Start installing metal siding
  • CANOPIESEast Canopy V103:Installing frames and glass
  • South Canopy V101:Installing frames and glass
  • West Canopy V102:Installing electrical and gyping lidsFinish installing WRB *
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Start installing trim and metal soffit panels
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Continue finishing siding after soffit is complete
  • Auditorium – West Elevation:
    • Finish installing vertical siding MWC
  • Auditorium – North Elevation:
    • Installing glass and pressure bar
    • Start installing beauty cap and flashing *
  • Auditorium – East Elevation:
    • Continue finishing siding *
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish installing MEP in 1st floor corridors
  • Start installing 1.5” metal deck
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Start installing MEP in ceiling, inspecting MEP in ceilings, and installing ceiling tiles
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finishing lids and walls
  • Lab Wing – Level 1 – Rough-in:
  • Start installing overhead MEP work in OTS *
  • Painting top out and OTS
  • Lab Wing – Level 1 – Commons Spaces:
    • Installing fireplace and MEP in fireplace cavity
    • Starting gyping walls
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Framing hard lids
    • Start installing MEP at hard lids
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Continue finishing MEP in grid
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Start finishing gyp *
  • Lab Wing –  Level 3 Rough-in:
    • Continue installing MEP in walls at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Installing disconnects *
  • Finish installing shaft frame, gyp, and finish
  • Elevator 2:
    • Continue installing elevator

Primary construction activities for the week of 11/04 thru 11/08 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Finish installing Z girts, insulation, and hat channels
    • Finish framing soffit
  • CANOPIESWest Canopy V102:Finish installing WRBStart installing frames and glass
  • Commons Wing Soffit:Finish installing hat channelStart installing trim and metal soffit panels
  • Lab Wing Soffit:Start painting vent in soffit and installing hat channel
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Start finishing siding after soffit is complete
  • Auditorium – West Elevation:
    • Installing beauty cap and flashing
  • Auditorium – North Elevation:
    • Finish installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish siding
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Installing scaffolding for MEPFP in Auditorium high ceiling *
  • Finish installing top for MEP to begin on 1st floor
  • Start installing MEPFP in Auditorium High Ceiling
  • Start installing MEP in 1st floor corridors
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Finishing drywall *
    • Painting
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish installing MEP at hard lids
    • Installing gyp at lids and walls (contingent on passing hard lid inspection)
    • Start finishing lids and walls
  • Lab Wing – Level 1 – Rough-in:
  • Start installing overhead MEP work in OTS
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Start finishing MEP in grid
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms
    • Installing gyp at lids and walls
    • Start finishing gyp
  • Lab Wing –  Level 3 Rough-in:
    • Finish installing MEP in Labs overhead
    • Finish framing walls at E/3 then clockwise
    • Finish installing MEP in walls at Doughnut
    • Start topping out gyp at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Installing disconnects
  • Start installing elevator equipment
  • Elevator 2:
    • Start installing elevator

Primary construction activities for the week of 10/28 thru 11/01 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Continue Z girts, insulation, and hat channels
    • Start framing soffit
  • CANOPIESEast Canopy V103:Installing frames and glass
  • South Canopy V101:Installing frames and glass
  • West Canopy V102:Finish framingInstalling electrical, and gyping the lidStart installing WRBCommons Wing Soffit:Painting vent in soffitStart installing hat channelLab Wing Soffit:Installing soffit WRB
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Finish installing glass, pressure bar, and vertical siding MWC
  • Auditorium – West Elevation:
    • Finish installing glass, pressure bar, and siding
  • Auditorium – North Elevation:
    • Finish installing glass and pressure bar
    • Siding in Armpit delayed for concrete to finish
    • Start installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish siding, beauty cap, and flashing – delayed for concrete work to finish
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish MEP in walls on 1st floor
  • Installing scaffolding for MEPFP in Auditorium high ceiling
  • Start installing top for MEP to begin on 1st floor
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Polishing floors
    • Finishing drywall
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Framing hard lids
    • Start installing MEP at hard lids
  • Lab Wing – Level 1 – Rough-in:
  • Finish installing OTS insulation
  • Painting top out and OTS
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Installing grid *
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms
    • Finish installing MEP at hard lids *
    • MEP inspection for hard lids
  • Lab Wing –  Level 3 Rough-in:
    • Continue installing MEP in Labs overhead
    • Continue framing walls at E/3 then clockwise
    • Installing MEP in walls at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Finishing shaft framing, gyp, and finish

Primary construction activities for the week of 10/21 thru 10/25 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab High Roof West:
    • Continue installing roofing
  • Penthouse Framing and Sheathing:
    • Installing insulation
    • Start installing scrim and hat channels
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Installing backer rod and caulk
    • Start installing glass and pressure bar
  • Auditorium – West Elevation:
    • Installing backer rod and caulk
    • Start installing glass and pressure bar
  • Auditorium – North Elevation:
    • Finish installing vertical siding MWC
  • Auditorium – East Elevation:
    • Finish installing beauty cap and flashing *
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • Continue framing bathroom shear walls and walls
  • Finish installing MEP at 2nd floor corridors
  • Installing seat sheathing
  • Start installing balance drywall at 2nd floor walls
  • Commons Wing – Auditorium:
    • Start installing scaffolding for finish and painting
  • Lab Wing – Level 1 Rough-in Remaining:
  • Start installing overhead MEP at OTS
  • Lab Wing –  Level 2 Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Offices and Conference Rooms
    • Finish installing MEP at ceilings
    • Start installing grid
  • Lab Wing – Level 2 – Labs:
    • Finish installing grid and necessary tiles
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms
    • Finish installing MEP at hard lids.
    • Start installing gyp walls and lids (contingent on MEP inspection)
  • Lab Wing –  Level 3 Rough-in:
    • Continue installing MEP in Labs overhead
    • Continue framing walls at E/3 then clockwise
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing fire protection
  • Installing cover for MEP
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
  • Finish finishing Gyp *
  • Stuff and spraying top of wall
  • Installing ceiling OTS insulation
  • Start painting the room
  • SITE IMPROVEMENTS
  • Courtyard:
    • Finish placing rock for East sidewalk

Start pouring E

Primary construction activities for the week of 10/14 thru 10/18 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • Start installing insulation
  • Lab High Roof West:
    • Start installing roofing
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Finish installing windows and vertical siding MWC
  • Auditorium – West Elevation:
    • Finish installing windows*
    • Installing vertical siding MWC
  • Auditorium – North Elevation:
    • Finish installing beauty cap and flashing
    • Installing vertical siding MWC
  • Auditorium – East Elevation:
    • Finish installing beauty cap and flashing
    • Continue installing vertical siding MWC
  • INTERIOR BUILDOUT
  • Mechanical Back of House:
    • Finish installing all MEP in mechanical spaces 1st floor
  • Commons Wing – Rough-in Framing:
  • Finish MEP in Walls on 2nd floor
  • Framing bathroom shear walls and walls
  • Start installing MEP at 2nd floor corridors
  • Lab Wing – Level 1 Rough-in Remaining:
  • Finish installing OTS insulation
  • Painting top out and OTS
  • Lab Wing –  Level 2 Rough-in:
    • Finish installing Electrical in OTS Commons
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Offices and Conference Rooms
    • Start installing MEP at ceilings
  • Lab Wing – Level 2 – Labs:
    • Installing grid and necessary tiles
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms
    • Start framing hard lids
    • Start installing MEP at hard lids.
  • Lab Wing –  Level 3 Rough-in:
    • Start installing MEP in Labs overhead
    • Start framing walls at E/3 then clockwise
  • Roof – West Penthouse ELEV Equip Room:
  • Installing elevator equipment
  • Start installing fire protection
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
  • Installing Gyp *
  • Start finishing Gyp *
  • SITE IMPROVEMENTS
  • Courtyard:
    • Pour 5 Heavy (FRPS) (Form, Rebar, Pour, Strip (FRPS))*
    • Pour 6 Heavy (FRPS) *
    • Start placing rock for East sidewalk

Primary construction activities for the week of 10/07 thru 10/11 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • All topping poured. Start installing Z Girt next week.
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Start installing windows
  • Auditorium – West Elevation:
    • Finish installing windows
    • Start installing backer rod and caulk
  • Auditorium – North Elevation:
    • Finish installing beauty cap and flashing
    • Installing vertical siding MWC
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • Finish MEP above and below Mezz decking
  • Start framing 1st floor walls
  • Start MEP in Walls on 2nd floor *
  • Lab Wing – Level 1 Rough-in Remaining:
  • Finish stuff and spray at head of walls
  • Installing OTS insulation
  • Lab Wing –  Level 2 Rough-in:
  • Finish installing Duct Work in OTS Commons and Offices
    • Continue installing Electrical in OTS Commons
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 3 Rough-in:
    • Start laying out walls and wall penetrations
  • Roof – West Penthouse ELEV Equip Room:
  • Continue installing Fire Protection *
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
  • Installing Gyp *
  • Start finishing Gyp *
  • SITE IMPROVEMENTS
  • Courtyard:
    • Finishing Pour 4 (Form, Rebar, Pour, Strip (FRPS))
    • Finishing Pour 5 Heavy (FRPS)
    • Finishing Pour 6 Heavy (FRPS)

Primary construction activities for the week of 09/30 thru 10/5 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • Rebar installed, pouring next week
  • WINDOWS & SIDING
  • Lab Wing – North Elevation:
  • Lab Wing – South Elevation:
  • Auditorium – East Elevation:
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical siding MWC
    • Install glass and pressure bar
    • Install beauty cap and flashing
  • Auditorium – North Elevation:
    • Start installing glass and pressure bar *
    • Start installing insulation and horizontal cleat
    • Install glass and pressure bar
    • Install beauty cap and flashing
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • MEP in Walls on 2nd floor *
  • Start installing upper seating framing
  • Install bathroom carriers
  • Frame first floors
  • MEP above and below  Mezz decking
  • Mechanical & Back of House:
    • Continue to install all MEP in Mechanical spaces on the 1st floor
  • Lab Wing – Rough in Remaining First Floor:
  • Finish installing Top Out
  • Start top out finish *
  • Lab Wing –  Level 2 Rough-in:
    • to install Hydronic piping in OTS Commons
    • Fire Protection in OTS commons
    • Continue to install Electrical in OTS Commons
    • Continue to install Plumbing in OTS Commons
    • Continue to install Duct Work in OTS Commons and Offices
    • Finishing all paint on 2nd floor *
  • Roof – West Penthouse ELEV Equip Room:
  • Installing Fire Protection *
  • Install cover for MEP
  • Roof – East Penthouse Stor, ELEV Lobby & Staging:
  • Install Gyp *
  • Start finishing Gyp *
  • Install ceiling ots insulation
  • Start painting room
  • SITE IMPROVEMENTS
  • Ramp:
  • Courtyard:
    • Finish grade
    • Begin pours