Primary construction activities for the week of 10/01 thru 10/05 will consist of the following:

Excavation for footings, forming for footings begins this week, backfilling and landscaping at ODFW with completion of fiber work, shut down to tie new water lines.

Asphalt patching between ODFW and West Wing will also take place this week.

Two waterline shutdowns Friday 10/5/2018:

First, Guin Library line- 7:00am to 9:00am

Second, Housing and Dining line- 1:00pm to 3:00pm