Primary construction activities for this week will include:

Deep Soil Mixing test panels to begin Tuesday transitioning into production panels by the end of the week

Vac-excavation and trenching near Guinn Librar for fiber optic lines to vault to take place starting Monday. This will impact East access road between project and Guinn Library.

Primary construction activities for this will include continued mobilization of Deep Soil Mixing equipment throughout the week and a waterline shutdown mid-week.

The waterline shutdown will take place Wednesday June 27th from 5:00 pm to 11:00 pm. This will effect water to the Visitors Center, East Wing, West Wing, Education Wing, Guin Library, NAL RSF, and Housing.

Below is an up to date schedule for the site.

MSIB CC 2018.06.11 schedule

Reported by Andersen Construction

Thursday, May 10 – Begin demolition of existing buildings

Monday, May 14 – Construct temporary ODFW driveway. Begin installing dewatering points.

Monday, May 21 – Begin sawcutting for parking lot for sewer installation.