Primary construction activities for the week of 9/17 thru 9/21 will consist of the following:

JAFEC and the Deep Soil Mixing equipment, will be demobilized 09/19.

Fiber work to ODF&W scheduled for 09/20 – 09/26, Access on foot path closed between OF&W and Ship Ops.

New water service work scheduled for 09/17, Ferry Slip Road will be closed for deliveries.

Coring in Lab Wing finished 09/19.

Attached is an up to date schedule for the project.

MSIB CC 2018.09.16

Primary construction activities for this week will include:

Deep Soil Mixing test panels to begin Tuesday transitioning into production panels by the end of the week

Vac-excavation and trenching near Guinn Librar for fiber optic lines to vault to take place starting Monday. This will impact East access road between project and Guinn Library.

Primary construction activities for this will include continued mobilization of Deep Soil Mixing equipment throughout the week and a waterline shutdown mid-week.

The waterline shutdown will take place Wednesday June 27th from 5:00 pm to 11:00 pm. This will effect water to the Visitors Center, East Wing, West Wing, Education Wing, Guin Library, NAL RSF, and Housing.

Below is an up to date schedule for the site.

MSIB CC 2018.06.11 schedule