Primary construction activities for the week of 2/18/2019 – 2/22/2019 will consist of:

Ramp- setting wall formwork, installing wall rebar, and closing formwork.

Structural Steel-

Stair 2- Installing clips, hangers, stairs, and handrails.

East Commons (Z1)- Installing metal decking and closure strips.

West Commons (Z2)- Bolting, plumbing, and welding. Installing metal decking and closure strips.

West Lab Wing (Z3)- Erecting steel, bolting, plumbing, and welding.

Center Lab Wing (Z4)- Erecting steel.

Mockup- Installing windows, green girts, and flashing behind green girts.

Primary construction activities for the week of 2/11/2019 – 2/12/2019 will consist of:

Core 1: Forming, pouring, and stripping the architectural fur wall.

Ramp: Fabricating walls and setting walls.

Structural Steel:

Stair 1: installing clips and hangers.

Stair 2: Delivery by EOW.

East Commons (Z1): Erecting steel, bolting, plumbing and welding.

West Commons (Z2): Erecting, bolting, plumbing, and welding.

West Lab Wing (Z3): Installing, shear tab clips, and erecting.

Center Lab Wing (Z4): Installing shear tab clips and misc metals.

East Lab Wing (Z5): Installing shear tab and misc metals.

Mockup: Framing, installing steel window surround, backing, weather barrier, and windows.

Primary Construction Activites for 02/04/2019-02/08/2019:

Core 1: Forming and pouring architectural fur wall.

Core 3: stripping level 4 core exterior.

Ramp: Stripping South and North footings. Fabricating walls and setting wall formwork.

Structural Steel: Stair 1- Installing stair and handrails.

Stair 2- Installing stair and handrails.

East Commons (Z1): Erecting steel, bolting, welding, and plumbing.

West Commons (Z2): Installing shear tab clips and misc. metals.

West Lab Wing (Z3): Installing Shear tab clips and misc. metals.

Mockup: Framing, installing steel window surround, backing, and weather barrier.

Primary construction activities for the week of 1/28/2019 – 2/1/2019 will consist of:

Core 1- Forming and pouring architectural fur wall.

Core 2- Level 4 will have rebar placed, formwork closed, and be poured.

Core 3- Level 4 will have rebar placed, formwork closed, and be poured.

Ramp- Forming and placing rebar, and pouring footings at the South wall.

Slab for Level 1 Air Handler Unit- pouring then striping the forms.

Mockups- Framing and sheeting.

Structural Steel- Stair 1 installing handrail.

– East Commons (Z1) installing shear tab clips. erecting steel Friday 2/10.

– West Commons (Z2) installing shear tab clips and misc. Metals.

Primary construction activities for the week of 01/21/2019- 01/25/2019 will consist of:

Core 2- Level 3 will be poured and inside core stripped, then start setting formwork and rebar for Level 4.

Core 3- Level 3 will be poured and stripped, then start setting formwork and rebar for Level 4.

Ramp- Forming and placing rebar at South Wall.

Slab for Level 1 Air Handler Unit- Install vapor barrier, forming, pour pads, and stripping pads.

Mockups- Install steel window surrounds, backing, and weather barrier.

Structural Steel- Installing clips and hangers for stair 1, and installing shear tab clips for east commons (Z1).

Primary construction activities for the week of 1/14/2019-1/18/2019 consist of:

Core 1- Level 4 Will have rebar and formwork set. Core 1 will also have a structural patch fix that will require jackhammering with a water wash.

Core 2- Level 3 will have rebar set, closing in formwork, and begin pouring level 3.

Core 3- Level 2 will be poured and stripped, then the forms will be moved up to level 3 and begin setting rebar.

Slab for Level 1 Air Handler Unit- will have drain rock and vapor barrier placed, then rebar for the slab will be set.

Mockups for installing steel window surrounds, backing, and weather barrier will be constructed.