Readjusting after Snow: Weekly Update 3/4-3/8

After last weeks snow postponed construction for several days, the crew are getting back out there and working hard to get caught up with last weeks schedule.

It will be a busy week at the clinic, the exterior stub walls will continue to go up as a continuation from late week and will carry over into the following week. Also over the course of this week crews will be working on the concrete pour for the stairs. This wonder sunny spring weather that we are starting out the week with will be perfect for the weather dependent roofing. We are keeping our fingers crossed that the snow is done for the season! Finally, the electrical rough in will begin on the second floor at the beginning of this week and is anticipated to take a couple of weeks.

Things will also be busy at the lecture hall building as we come out of our snow days. the framing of the lecture hall will continue into this week and next, as will the installing of the piping for the fire suppression system. Though it is plan to be wrapped up by the end of the week. The current weather will also be helpful at the lecture hall as they plan to start the weather dependent roofing this week. After all of this, the lecture hall will start to look more like a building than its current black-boxy form. That’s because the exterior brick veneer will start to go up and the new lecture hall will blend seamlessly in with the existing Magruder Hall.

With all the major working happening at the clinic and lecture hall this week, things will be a little quieter at the LINAC addition. The only major activity over the next couple of weeks will be the framing.

Print Friendly, PDF & Email

Leave a Reply

Your email address will not be published. Required fields are marked *