A Presidential Weekly Update: 2/18-2/22

As we kick this week off with Presidents Day, our crew continues to blast through construction, like the blasts that created our founding fathers on Mt. Rushmore.

Once again, the majority of the work this week will be happening at the clinic. The exterior stub walls are still going up and the footings for the entry vestibule (two door system entry) will be started and completed by the end of the week. The second floor will see the framing be finished out and plumbing, mechanical, and electrical rough-ins will be completed but the end of the week.

Weather dependent, both the clinic and lecture hall could be some roofing action starting to take place.

Also at the lecture hall, the exterior stub walls will continue to go up through the beginning of next week. Framing inside the lecture hall will begin early this week and carry through the beginning of March. The piping for the fire suppression system will be closed out by end of day, Wednesday.

The slab edge form at LINAC as been pushed over into this week, the concrete pour is now expected to happen next week.