Fortis and the crew at kicking off December strong and steady. We are truly appreciative of everyone working on the Magruder Addition this Holiday Season. We wish every member of the Magruder Team and their families a warm and joyful holiday.

In the meantime, at the Clinic we will continue to see the CMU brick installation continue, as the building to take shape.

The new storm and sanity lines will be installed this week at the Lecture hall location.

Finally, we will see a lot going on at the LINAC addition as they rough in the mechanical, electrical and plumbing before the concrete pour for the walls on Thursday the 6th.