Weekly Update 11/13-11/16

After taking time over the weekend to thank and remember the veterans who have served our country, Fortis is ready to hit the ground running with another busy week!

At the clinic location, the majority of the work will focused on continuing the installation of the CMU over the next several weeks. Expect the lecture hall location to be more active over the next couple of weeks.

Pacific Excavation will be working on the underground storm piping and T. Gerding will be pouring concrete for the plinths on Wednesday, November 14th through Thursday the 15th.

Above you can see the detail drawing of how the plinth will look on the left. To the right, you can see the highlighted areas where these plinths will be located.

Overall E.C. Electric will continue investigating and working on the conduit installation for the lecture hall. As well as, working on the electrical piping inside the existing clinic, along side Hammerquist, as they investigate and start routing for plumbing.

The majority of the work at the LINAC location will include placing the footing rebar for the concrete footing pour on 11/15.  Around this, T. Gerding will continue forming the walls over the next several weeks.

As always, check out our Schedule and Photos tabs to stay up to date the the latest 4-week schedule plan and on site pictures.

Print Friendly, PDF & Email