Construction Update 5/17 thru 5/21

Posted May 17th, 2010 by evanjose

For May 17th – May 21st, 2011, please see the following for what construction will impact.

Significant Impact(s):

  • Limited parking on 17th street (see below for details)
  • Traffic control revisions on Western between 16th & 17th
  • Equipment Noise

Monday:   (7:30am – 4:30pm)

  • Prep for temporary trailer installation delivery (Fortis layout, foundations)
  • Construct temporary construction driveway into site (rock trucks, front-end loader & compactor)
  • Begin mass excavation of the building pad (track hoe, back hoe & rock trucks)
  • Excavate for new sewer connection to the construction trailer (track hoe, back hoe)

Tuesday:  (7:30am – 4:30pm)

  • Delivery of Fortis construction trailers (4 over-size truck deliveries)
  • Installation of construction trailers (level & anchor foundations & hook-up utilities)
  • Construct temporary construction driveway into site (rock trucks, front-end loader & compactor)
  • Continue mass excavation of the building pad (track hoe, back hoe & rock trucks)
  • PPL – Method of Procedure coordination meeting for 17th Street existing power (10AM)
  • Installation of site construction signage (Fortis)

Wednesday:   (7:30am – 4:30pm)

  • Installation of construction trailers (level & anchor foundations & hook-up utilities)
  • Continue mass excavation of the building pad (track hoe, back hoe & rock trucks)
  • NW Natural Gas – coordination meeting for gas line to be abandoned in 17th Street
  • Installation of construction temp utilities – power and water (back hoe)

Thursday:       (7:30am – 4:30pm)

  • Construct deck and stairs at Fortis construction trailers
  • Installation of construction trailers (level & anchor foundations & hook-up utilities)
  • Continue mass excavation of the building pad (track hoe, back hoe & rock trucks)
  • Installation of construction temp utilities – power and water (back hoe)

Friday:       (7:30am – 4:30pm)

  • Construct deck and stairs at Fortis construction trailers
  • Installation of construction trailers (level & anchor foundations & hook-up utilities)
  • Continue mass excavation of the building pad (track hoe, back hoe & rock trucks)
  • Installation of construction temp utilities – power and water (back hoe)
  • Excavate parking lot north of A Avenue (back hoe, front-end loader & compactor)